Kavşak Bendi Dam

Kavşak Bendi Dam
Location of Kavşak Bendi Dam in Turkey
Official name Kavşak Bendi Barajı ve HES
Country Turkey
Location Kozan/Aladağ
Coordinates 37°33′45.28″N 35°31′45.84″E / 37.5625778°N 35.5294000°E / 37.5625778; 35.5294000Coordinates: 37°33′45.28″N 35°31′45.84″E / 37.5625778°N 35.5294000°E / 37.5625778; 35.5294000
Status Operational
Construction began 2008
Opening date 2013
Owner(s) Enerjisa Power Generation Inc.
Dam and spillways
Type of dam Embankment, concrete-face rock-fill
Impounds Seyhan River
Height (foundation) 88 m (289 ft)
Height (thalweg) 73 m (240 ft)
Length 186 m (610 ft)
Elevation at crest 323 m (1,060 ft)
Width (crest) 8 m (26 ft)
Dam volume 1,215,000 m3 (1,589,160 cu yd)
Spillway type Controlled
Spillway capacity 5,053 m3/s (178,400 cu ft/s)
Reservoir
Creates Kavşak Bendi Reservoir
Total capacity 30,000,000 m3 (24,321 acre·ft)
Active capacity 7,560,000 m3 (6,129 acre·ft)
Catchment area 13,200 km2 (5,097 sq mi)
Surface area 1.42 km2 (1 sq mi)
Max. length 11 km (7 mi)
Normal elevation 318 m (1,043 ft)
Power station
Name Kavşak Bendi Hydroelectric Station
Coordinates 37°32′19.83″N 35°31′29.90″E / 37.5388417°N 35.5249722°E / 37.5388417; 35.5249722 (Kavşak Bendi Hydroelectric Station)
Commission date 2013-2014
Type Conventional, diversion
Hydraulic head 84.81 m (278 ft) (net)
Turbines 3 x 59 MW Francis-type
Installed capacity 177 MW[1]
Annual generation 741 Gwh

The Kavşak Bendi Dam is a concrete-face rock-fill dam on the Seyhan River bordering Kozan and Aladağ districts in Adana Province, Turkey. Construction on the dam began in 2008 and the first generator was commissioned in 2013. The two remaining generators were commissioned by April 2014.[2] The primary purpose of the dam is hydroelectric power generation. Water is sent about 2.5 km (1.6 mi) downstream where it meets the power station which contains three 59 MW Francis turbine-generators.[3][4]

See also

References

  1. "HRW Briefings". HydroWorld. 1 March 2009. Retrieved 31 May 2013.
  2. "Turkey's Enerjisa says Kavsak Bendi HPP operating at full capacity". See News - Renewables. 14 April 2014. Retrieved 22 December 2014.
  3. "Kavsak Bendi Hydroelectric Power Plant Capacity Increase Project" (PDF). EnerjiSA. Retrieved 31 May 2013.
  4. "Official construction starts for Verbund plants in Turkey". ICIS. 22 October 2008. Retrieved 31 May 2013.
This article is issued from Wikipedia - version of the 9/17/2015. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.