Arkun Dam

Arkun Dam
Location of Arkun Dam in Turkey
Country Turkey
Location İspir, Erzurum Province
Coordinates 40°40′34.25″N 41°17′21.09″E / 40.6761806°N 41.2891917°E / 40.6761806; 41.2891917Coordinates: 40°40′34.25″N 41°17′21.09″E / 40.6761806°N 41.2891917°E / 40.6761806; 41.2891917
Purpose Power
Status Operational
Construction began 2011
Opening date 2014
Owner(s) State Hydraulic Works
Dam and spillways
Type of dam Embankment, earth-fill
Impounds Çoruh River
Height (foundation) 188 m (617 ft)
Height (thalweg) 140 m (459 ft)
Dam volume 6,774,345 m3 (8,860,509 cu yd)
Reservoir
Catchment area 6,853 km2 (2,646 sq mi)
Power station
Commission date June 2014
Hydraulic head Downstream: 225 m (738 ft) (gross)[1]
Toe: 225 m (738 ft) 121 m (397 ft) (nominal)[2]
Turbines Downstream: 3 x 75 MW Francis-type
Toe: 2 x 5.96 MW Francis-type
Installed capacity 236.92 MW
Annual generation 788 GWh (estimate)

The Arkun Dam an embankment dam on the Çoruh River near İspir in Erzurum Province, Turkey. Construction began in 2011 and the primary purpose of the dam is hydroelectric power generation. It is part of the Çoruh Development Plan and its construction is being supervised by Turkey's State Hydraulic Works. The dam and power plant were completed early, in June 2014. Water from the dam's reservoir supplies two power stations; one at the dam's toe (base) (11.92 MW) and the other downstream (225 MW) in Artvin Province.[1][3]

See also

References

  1. 1 2 Sucu, Sezai. "Çoruh Basin Projects" (PDF) (in Turkish). State Hydraulic Works. Retrieved 7 May 2013.
  2. "Introductory File For Capacity Increase Within Arkun Dam and HEPP" (PDF). Dolsar. November 2010. Retrieved 7 May 2013.
  3. "As arkun Dam and HEPP was completed in a short period of 4 years." (in Turkish). State Hydraulic Works. 18 June 2014. Retrieved 25 February 2016.
This article is issued from Wikipedia - version of the 7/24/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.