Grand Rapids Medical Corridor North Pedestrian Tunnel
pedestrian tunnel under Michigan Street | |
Overview | |
---|---|
Location | Grand Rapids, Michigan |
Coordinates | Coordinates: 42°58′13.8″N 85°39′55.4″W / 42.970500°N 85.665389°W |
Status | open |
Start | Butterworth Hospital |
End | Lemmen-Holton Cancer Pavilion |
Operation | |
Work begun | 15 December 2005 |
Constructed | excavated through grouted glacial till, shotcrete lined |
Opened | 26 May 2006 |
Owner | Spectrum Health |
Character | pedestrian tunnel |
Technical | |
Length | 130 feet (40 meters) |
Tunnel clearance | 20 feet |
Grade | level |
The Grand Rapids Medical Corridor North Pedestrian Tunnel is a tunnel in Grand Rapids, Michigan connecting the Lemmen Holton Oncology Center with Butterworth Hospital and Helen DeVos Children's Hospital.
Construction
The tunnel passes under Michigan Street, a busy thoroughfare. Construction was accomplished using the New Austrian Tunneling method without disrupting the traffic moving on the street above.[1] The tunnel was mined[2] through glacial till, which was grouted with Sodium silicate to stabilize it prior to digging the tunnel.[3] The tunnel is lined with 15 inches (380 mm) of shotcrete.
In 2007, it received the ABC/WMC Construction Award from the Associated Builders and Contractors–Western Michigan Chapter.
References
- ↑ Almeraris, Gary; Mariucci, Bill, eds. (2009) [2007]. "NATM Through Clean Sands- The Michigan Street Experience". Rapid Excavation and Tunneling Conference: Proceedings 2007. SME. pp. 988–997. ISBN 978-0-87335-304-5.
- ↑ "Grand Rapids Medical Corridor North Pedestrian Tunnel". Gall Zeidler Consultants. Retrieved 4 July 2010.
- ↑ Nicholson Construction (2010). "Michigan Street Tunnel". Retrieved 4 July 2010.
This article is issued from Wikipedia - version of the 11/20/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.