Black Sea Transmission Network
Black Sea Transmission Network | |
---|---|
Location | |
Country |
Georgia Turkey |
General direction | north–south |
From |
Gardabani Zestafoni |
Passes through | Akhaltsikhe |
To | Borçka |
Ownership information | |
Operator | Energotrans |
Construction information | |
Contractors | Siemens |
Construction started | 2010 |
Expected | 2013 |
Technical information | |
Type | overhead line |
Type of current | AC/HVDC/AC |
Total length | 283 km (176 mi) |
Power rating | 700 MW |
AC Voltage | 500/400 kV |
DC Voltage | 96 kV |
Number of circuits | 1 |
The Black Sea Transmission Network is a project for electric power transmission from Georgia to Turkey.
Technical description
The project foresees a rehabilitation and expansion of the existing transmission system. An overhead transmission line with a total length of 247 kilometres (153 mi) will be built from the existing Gardabani and Zestafoni substations to the new Akhaltsikhe substation situated at 41°42′26″N 43°06′35″E / 41.70722°N 43.10972°E. The line between Gardabani and Akhaltsikhe will be 187 kilometres (116 mi), of which 86 kilometres (53 mi) is a rehabilitation of the existing line and 101 kilometres (63 mi) will be a new line. The line between Zestafoni and Akhaltsikhe is 59 kilometres (37 mi) long, of which 35 kilometres (22 mi) is a rehabilitation of the existing line and 24 kilometres (15 mi) will be a new line. The 500 kV overhead line will be a single-circuit transmission line.[1]
At Akhaltsikhe substation two back-to-back high-voltage direct current stations, each with a capacity of 350 MW will be installed. A 400 kV AC overhead line will connect it with Borçka substation in Turkey. About 35 kilometres (22 mi) of it will run in the territory of Georgia.[1] The first HVDC back-to-back station would be operational in May 2012 and the second one in May 2013. This link will be built by Siemens.[2][3]
Financing
The project is financed by several European finance institutions. The European Investment Bank and the European Bank for Reconstruction and Development lend €80 million both while the German development bank KfW peovides €100 million in the form of a grant (€25 million) and a long-term loan (€75 million, €20 million Development Bank of Austria, w:de:Oesterreichische Entwicklungsbank (OeEB) risk participation).[4][5] The project is developed by the Georgian state-owned transmission system operator Energotrans.[2][3]
See also
References
- 1 2 "EIB - Black Sea Transmission Network Project (GE-Tbilisi)". Development Gateway, Inc. Retrieved 2010-08-25.
- 1 2 "Black Sea HVDC interconnection work awarded to Siemens". Power Engineering International. PennWell Corporation. 2010-08-24. Retrieved 2010-08-25.
- 1 2 van Loon, Jeremy (2010-08-24). "Siemens to Install High-Voltage Power Line, Connecting Georgia and Turkey". Bloomberg. Retrieved 2010-08-25.
- ↑ "Black Sea Power Transmission Project, Georgia". Global Transmission Report. 2010-05-01. Retrieved 2010-08-25.
- ↑ "Improving Power Infrastructure in Georgia" (Press release). KfW. 2010-04-14. Retrieved 2010-08-25.